APS SÉNÉGAL–POLITIQUE–DIPLOMATIE / Un universitaire explique les dessous de la diplomatie de bon voisinage prônée par Dakar APS SENEGAL-AFRIQUE-DIPLOMATIE / A Banjul, Bassirou Diomaye Faye ”sera accueilli comme il se doit”, assure un officiel gambien APS SENEGAL-SIERRALEONE-COOPERATION / Le vice-président de la Sierra Leone reçu en audience par Bassirou Diomaye Faye APS SENEGAL-AFRIQUE-SOCIETE / Dakar et Banjul invités ‘’à jouer un rôle pilote’’ dans le processus d’intégration sous-régionale APS SENEGAL-LITTERATURE / L’Harmattan Sénégal présente deux ouvrages sur le blanchiment de capitaux dans l’UEMOA, samedi APS SENEGAL-AFRIQUE-CINEMA / Un expert salue la solidarité féminine mise en avant dans certains films pour sensibiliser sur le réchauffement climatique MAP CAN de futsal (demi-finale) : Le Maroc en finale et en Coupe du monde après sa victoire face à la Libye (6-0) MAP CAN de futsal (demi-finale): Le Maroc évince la Libye (6 – 0) se qualifie pour le Mondial MAP Le ministre malien de l’Agriculture salue les progrès du Maroc en matière de gestion d’eau et de barrages MAP Océanographie: Madagascar souhaite tirer profit de l’expérience marocaine (ministre malgache)

President commissions gas usage for Karpowership


  8 Décembre      41        Economie (20953),

 

Accra, Dec. 8, GNA – President Nana Addo Dankwa Akufo-Addo has commissioned the usage of gas from the Atuabo Gas Processing Plant to power the relocated 450 megawatt Karpowership at the Sekondi Naval Base in the Western Region.

The conversion of the Karpowership from heavy fuel oil usage to natural gas for power generation is expected to save the country a monthly take-or-pay cost of 40 million dollars and projected annual savings of 480 million dollars.

At a valve-opening ceremony on Saturday, President Akufo-Addo said the conversion was in line with his Government’s overarching plan of promoting the use of gas as the primary fuel for power generation in the country.

He said the switch was to ensure the maximum utilisation of indigenous gas in the Western Region to reduce, and to eventually eliminate, the financial consequences under the take-or-pay obligation of the Karpowership Contract.

“The arrangement that we have made with the companies is that the gas that comes out of the ground belongs to us. We are not paying for it. If it is ours, we should use it,” he said.

With the development, Karpowership will take approximately 50 per cent of the volume of the take-or-pay Sankofa gas for power generation over the remaining period of the Power Purchase Agreement (PPA).

Specifically, the switch of the Karpowership to natural gas would save electricity users an amount of 170.5 million dollars per year, and a projected amount of 1.2 billion dollars over the remaining term of the Contract, by way of reduced electricity charges to consumers.

Noting further the gains to be made by the arrangement, the President said using gas as the primary source of power generation would post significant returns for the country over the next decade.

Moreover, the use of gas, he noted, would bring down the cost of electricity and, thus, provide a secure and cheaper source of powering the economic and industrial growth of the country.

Dans la même catégorie