AIP Ladji Abou Sanogo installé officiellement dans ses fonctions de délégué général de l’UNJCI ACP La pastèque augmente la vitalité des vaisseaux sanguins, selon un médecin ACP Dr Nico ou génie artistique dans le fondement de la musique congolaise moderne (Arthur Kayumba) ACP La 20ème édition du Festival national de Gungu confirmée du 24 au 28 septembre 2020 au Musée national de la RDC AGP Siguiri/Société : Renforcement des capacités des jeunes au montage des projets. AGP Mamou/environnement : 10 hectares de forêts reboisés par les chasseurs de Teguereya APS LE PROJET GOYN PRÉSENTÉ AUX ACTEURS DE DIOURBEL APS LE CORONAVIRUS IMPOSE SA LOI AUX ASC APS COVID-19 : LE PIB RÉEL DU SÉNÉGAL SE CONTRACTERA DE 0,7 % EN 2020 (FMI) APS 30 FILLES DU CENTRE SAUVEGARDE DE THIÈS FORMÉES EN COUTURE

Vice President inspects construction works on Tono Irrigation project


  11 Septembre      8        Politique (11245),

   

   Tono (UE), Sept 11, GNA – Vice President Dr Mahamudu Bawumia has paid a working visit to the Tono Irrigation Project in the Kassena-Nankana Municipality of the Upper East Region to inspect the progress of rehabilitation works.
   Two weeks of torrential rainfall in October 2019 washed away parts of the Tono Irrigation facility including the retaining walls, the spillway, the dam floor and the embankment causing the water to overflow the laterals and canals.
   The spilt water submerged about 850 hectares of rice and vegetable farms in the area.
   Dr Bawumia on a tour to the area last year promised that government would fix the problem and repair the damage.
   The Tono Irrigation project, which was constructed by the government in 1985 to promote agriculture production in the area and its environs, had not been rehabilitated, making the facility to operate below capacity.
    The rehabilitation of the Multipurpose Tono Irrigation Project at a cost of about $30 million started in 2018 and would be completed in 2021.
   The project, which has funding support from the World Bank and United States Agency for International Development (USAID), was awarded to Top International Engineering Cooperation, (TIEC), a Chinese construction firm.
   The facility could irrigate an area of about 4,000 hectares of farmlands, however, as a result of the breakdown of the major canals and laterals that carry water from the dam to farmlands, only 1,300 hectares of farmlands are being used.
    The project when completed would not only boost agriculture production in the Kassena-Nankana and Builsa communities but is expected to feed the new water treatment plant under construction at Tono which when completed would supply treated water to Navrongo, Paga, Zuarungu, Bolgatanga and environs by the Ghana Water Company Limited
    Mr Sabastian Bagina, the Operations Manager, Irrigation Company of Upper Region (ICOUR), who briefed the Vice President, said the spillway was about 60 metres wide and 500 metres long.
   He said the contractor would move back to the site when the water receded.
   Mr Bagina said that about 400,000 farmers directly benefited from the Tono Irrigation Project.
   “The contractor has been on the ground working to try and protect the control structure itself before any spillage, he was able to achieve that to some extent and spillage started about five days ago and when the water level recedes he will resume work to complete it.”
   The Vice President, who is on a two-day tour of the region, charged the contractor to ensure that the quality of work stood the test of time to protect the dam from being damaged.
   The Vice President was accompanied by Mr Eric Nana Agyemang Prempeh, the Director-General of NADMO, Dr Nurah Kwaku, Minister of State for Agriculture, Mr Anthony Kabo, Deputy Minister of Roads and Highways, Mr Ambrose Dery, Minister for the Interior, Mr Stephen Mahamudu Yakubu, Ghana Ambassador to Morocco, Madam Tangoba Abayage, the Upper East Regional Minister among other government officials.