APS JOJ 2026 : 2022 SERA LE DÉBUT D’UNE SÉRIE D’ACTIONS CONCRÈTES SUR LE TERRAIN (ORGANISATEURS) ANP Niger : Bientôt une école de l’Armée de l’Air à Agadez et un centre de formation de 5000 jeunes militaires par an à Keita (Président Bazoum) GNA Minister asks illegal sand miners to stop operation or face the law ANP Ouverture de l’école militaire supérieure de Niamey : Une « nécessité lancinante »pour le Niger, selon le Président Mohamed Bazoum AGP Gabon : Les Présidents des Juridictions désormais outillés AGP Gabon : Les enjeux du Congrès international des Barreaux expliqués à Ali Bongo Ondimba ACP Le Premier ministre Sama Lukonde s’engage dans l’opération « Zéro trou à Kinshasa » ACP Organisation à Kinshasa d’une table ronde sur la mise en place d’un fonds national de réparation en faveur des victimes de violences sexuelles ACP Le Sénat vote le projet de loi autorisant la prorogation de l’état de siège au Nord-Kivu et en Ituri. AGP Gabon : Le Camp Missambo contre le report du congrès de l’Union nationale

EU supports energy sector with additional 9.7 million Euros


  2 Février      9        Human Development (188), Migration (1080),

   

Accra, Feb. 2, GNA– The European Union (EU), through the French Development Agency- Agence Francaise Development (AFD) has approved a 9.7 million Euros grant to Ghana Grid Company Limited (GRIDCo) to boost infrastructure works on its Kumasi-Bolgatanga Transmission Project.

The aim of the project is to enhance and upgrade electricity supply and access to the Northern Regions of Ghana. It will also boost export of power to the sub-region under the West African Power Pool (WAPP), commencing with Burkina Faso.

The grant was co-signed by both Ms Diana Acconcia, EU Ambassador to Ghana and Ms Anne-Sophie Ave, French Ambassador to Ghana and Mr Christophe Cottet, Country Director of AFD and Mr Jonathan Amoako-Baah, Chief Executive Officer of GRIDCo, both signing on behalf of their respective institutions.

The project is considered a key link and priority in the West African Power Pool. It was initially financed with 174 million dollars from AFD to GRIDCo and 4.8 million Euros technical assistance grant from the EU.

The grant, would facilitate the early completion of the project which is behind schedule, to ensure sustainable and reliable electricity supply in Ghana and the sub-region.

The approval of the grant is also a recognition of the several strategic measures and prudent fiscal policies undertaken by the last Board of GRIDCo.

For a greater part of the last three years, work on the 330 kV transmission line project from Kumasi to Bolgatanga slowed down as AFD was compelled to stop paying contractors working on the project.

This was due to severe liquidity challenges resulting in GRIDCo inability to ‘service’ the initial AFD US$174 million loan and other similar obligations.