AGP Dialogue national : le président Oligui Nguema échange avec les membres du bureau AGP Gabon : Bientôt un recensement des biens de l’Etat AGP Coopération Gabon-France : un forum économique en perspective APS SENEGAL-PRESIDENTIELLE / Bassirou Diomaye Faye reçu en audience par Macky Sall MAP Afrique du Sud: Zuma exclu des prochaines élections (Commission électorale) MAP La CAF annonce les dates des finales de la Ligue des Champions et de la Coupe de la Confédération MAP Afrique du Sud: 45 morts dans un accident d’autocar au Limpopo APS SENEGAL-ITALIE-TRANSPORTS / ITA Airways va inaugurer en juillet une ligne Rome-Dakar APS SENEGAL-ENVIRONNEMENT / Bonne amélioration des taux d’accès à l’eau et à l’assainissement (expert) ANP Signature de convention entre le Niger et la Société WAPCO Niger pour un programme de formation de talents à Southwest Petroleum University de Chine

Power fluctuations will soon be over-Energy Minister


  27 Avril      50        Economie (20813),

 

By Godwill Arthur-Mensah, GNA
Accra, April 27, GNA-The Minister of Energy, Dr Matthew Opoku Permpeh, has entreated Ghanaians to exercise patience as government is investing financial resources towards the upgrading of the power operating system in the country.
That, he said, would ensure efficient and reliable power supply to both domestic and commercial power consumers to improve their businesses.
Dr Opoku Prempeh gave the assurance when he led a delegation, comprising officials from the Millennium Development Authority, Electricity Company of Ghana, and Volta River Authority, to inspect the Kasoa Bulk Supply Point, on Tuesday.
The country in recent months have witnessed frequent power cuts, especially parts of the national capital, Accra, resulting in public outcry.
A section of the public has accused government of not telling Ghanaians the truth about the power situation, and suspected that government has no money to buy fuel for the power plants.
It is in this light that the Energy Minister, over the past two weeks, had been touring some power projects being undertaken by government to ending the power outages.
The Kasoa BSP is 435 MVA, which is about 50 per cent complete, and expected to improve power supply to Winneba, Mallam and parts the Greater Accra and Central regions.
The project is being implemented by the Millennium Development Authority (MiDA), under the Ghana Power Compact Two and falls under the Millennium Challenge Corporation (MCC), which the US government provided US$308 million to the government of Ghana, to improve its energy needs and curb power transmission losses.
Mr Matin Esson Benjamin, the Chief Executive Officer of MiDA said the Kasoa BSP was being constructed by Semens Engineering at a cost of US$50 million and expected to be completed in August, this year.
He said the construction of the Kasoa BSP was timely, as it would improve power supply to residents of Mallam, Kasoa, Winneba among others and would benefit about 300, 000 residents in parts of the Greater Accra and Central regions.