GNA Propak supports Ghana’s aspirations to boost export of made-in-Ghana brands GNA Power Outages: Disability Federation calls for timetable GNA Ministry of Works and Housing launches BENCHH 2024 GNA Bulk Oil Distributors object to government’s plan to designate BEST sole off-taker GNA Prices of vegetables, and cereals up in Cape Coast GNA Ghana’s Seed Association AGM reflects moment of transition and growth GNA SWAG applauds Dreams FC’s incredible CAF Confederation Cup journey  GNA Captain One Golf Society gets financial support from fitness and wellness expert Roberta GNA MOYS commiserate with family of late Dr. Owusu-Ansah MAP Morocco’s Experience in Implementing SDGs Highlighted in Addis Ababa

President commissions Pokuase substation


  20 Octobre      29        Economy (15127), Environment (3678),

   

Pokuase, Oct. 20, GNA- President Nana Addo Dankwa Akufo-Addo Wednesday commissioned the Pokuase Bulk Supply Point (BSP) Substation to increase the reliability of power supply to homes, businesses and industrial plants in the northern parts of Accra.
With a total capacity of 580 Mega Volt Ampere (MVA), the 330 KVA Pokuase BSP, the fifth in Accra, is the largest and most technologically advanced substation in Ghana.
It will improve power supply quality and reliability to the more than 350,000 utility consumers in Pokuase, Nsawam, Achimota, Anyaa, Sowutuom, Kwabenya, Ashongman, Legon, Haatso, Agbogba, Adenta and Aburi communities.
The facility will also reduce transmission and distribution losses, and improve the financial viabilities of the Ghana Grid Company (GRIDco) and the Electricity Company of Ghana (ECG).
The construction of the USD47 million facility commenced in April 2019 and was completed in May 2021. It was funded by the United States of America through the Millennium Challenge Corporation (MCC).
At an inaugural ceremony, President Akufo-Addo said the BSP project not only gave the assurance of stable power supply, « but also reminds us of how far we have come from the days of widespread, power outages and the phenomenon of Doom. »
He noted that any country that aspired to industrialise with the overarching goal of guaranteeing a decent quality of life for its people must ensure that its citizens had access to stable, efficient and affordable power supply.
« Electricity is no longer a luxury. But rather a basic necessity, and we must commit ourselves to working hard and ensuring that we achieve universal coverage in this country as soon as possible to spur economic growth, » he said.