MAP Morocco’s International Agriculture Exhibition Strengthens African Cooperation GNA US investors table market concerns before Ghana’s Trade Minister MAP Morocco Praised as Agricultural Model by Ivorian Minister GNA Krobo branch of National Tailors, Dressmakers Association supports 24-Hour Economy -Chairman GNA Ghana Hubs Network holds annual general meeting in Takoradi GNA Telecel Ghana announces presence in Kumasi, promises innovation in network services GNA Government advised to adopt digital systems for credit management GNA UEFA U16 Tournament: Black Starlets bounce back with victory over Serbia  GNA Ghanaman Soccer Centre of Excellence gets facelift Inforpress Judo: Djamila Correia e Silva conquista prata no Campeonato Africano no Egipto

EU supports energy sector with additional 9.7 million Euros


  2 Février      34        Human Development (233), Migration (1217),

   

Accra, Feb. 2, GNA– The European Union (EU), through the French Development Agency- Agence Francaise Development (AFD) has approved a 9.7 million Euros grant to Ghana Grid Company Limited (GRIDCo) to boost infrastructure works on its Kumasi-Bolgatanga Transmission Project.

The aim of the project is to enhance and upgrade electricity supply and access to the Northern Regions of Ghana. It will also boost export of power to the sub-region under the West African Power Pool (WAPP), commencing with Burkina Faso.

The grant was co-signed by both Ms Diana Acconcia, EU Ambassador to Ghana and Ms Anne-Sophie Ave, French Ambassador to Ghana and Mr Christophe Cottet, Country Director of AFD and Mr Jonathan Amoako-Baah, Chief Executive Officer of GRIDCo, both signing on behalf of their respective institutions.

The project is considered a key link and priority in the West African Power Pool. It was initially financed with 174 million dollars from AFD to GRIDCo and 4.8 million Euros technical assistance grant from the EU.

The grant, would facilitate the early completion of the project which is behind schedule, to ensure sustainable and reliable electricity supply in Ghana and the sub-region.

The approval of the grant is also a recognition of the several strategic measures and prudent fiscal policies undertaken by the last Board of GRIDCo.

For a greater part of the last three years, work on the 330 kV transmission line project from Kumasi to Bolgatanga slowed down as AFD was compelled to stop paying contractors working on the project.

This was due to severe liquidity challenges resulting in GRIDCo inability to ‘service’ the initial AFD US$174 million loan and other similar obligations.