MAP SAR la Princesse Lalla Meryem préside le Conseil d’Administration des Oeuvres Sociales des FAR MAP Signature de deux mémorandums d’entente entre le Maroc et Djibouti dans le domaine de la santé et de la protection sociale ANP La CAIMA offre 3043,75 tonnes d’engrais d’une valeur de 821 millions de CFA au FSSP APS SENEGAL-COMMERCE / Des faux médicaments, des cuisses de poulet et du cannabis saisis par les unités maritimes de la Douane APS SENEGAL-METEO / Le centre et l’ouest seront recouverts progressivement par une couche de poussière dense (météo) MAP Rwanda: le volume des investissements dépasse 2,4 milliards de dollars en 2023 MAP Match USMA-RSB: la CAF rejette l’Appel interjeté par le club algérois et confirme les décisions de la commission des clubs (FRMF) MAP Madagascar: Plaidoyer pour la création d’un réseau de transport public écologique à Antananarivo MAP Abidjan: le RIARC et le REFRAM signent une déclaration sur le renforcement du dialogue avec les plateformes numériques globales APS SENEGAL-SOCIETE / Santé oculaire : des stratégies et orientations prioritaires en cours d’identification

AMA hands over school to Accra Wesley Girls Senior High


  3 Février      39        Société (45143),

 

By Albert Allotey, GNA
Accra, Feb. 3, GNA-The Accra Metropolitan Assembly (AMA) has handed over a six-unit classroom block to the Accra Wesley Girls Senior High School at Kaneshie in Accra.
The facility was funded by the World Bank under the Ghana Secondary Education and Improvement Project (GSEIP).
Speaking at a brief handing over ceremony, Mr Mohammed Adjei-Sowah, the Accra Metropolitan Chief Executive said the completion of the project was timely as it would help to ease congestion in classrooms, especially during this COVID-19 period.
He said the AMA would work closely with the Ghana Education Service (GES) to develop a master-plan that would establish guidelines to improve the physical conditions of school structures and create conducive atmosphere for learning, which would last for decades.
Mr Sowah said the Assembly would also collaborate with the Member of Parliament for Okaikwei South, Madam Darkoa Newman and other stakeholders to improve teaching and learning in the schools.
Mr Herbert Kwadwo Abeka, the Contractor of the project said the contract was awarded in June 2019, but there was some technical challenges and the COVID-19 pandemic, which stalled its progress until the last six months of 2020 when work began.
He said the initial amount for the project was GH¢1.8 million, but shot up to GH¢ 2.2 million due to redesigning works.
Madam Leticia Bray, the Headmistress of the Accra Wesley Girls Senior High expressed gratitude to all stakeholders involved in the completion of the edifice and promised to make good use of it.
“I will like to assure all stakeholders that this six-unit classroom block would be put to good use to promote effective teaching and learning,” she said.