MAP La Namibie découvre un gisement pétrolier de plus 10 milliards de barils MAP Burkina Faso : une soixantaine de terroristes neutralisés par l’armée dans l’est du pays APS SENEGAL-UNIVERSITE-PARTENARIAT / Signature d’une convention entre l’UCAD et le complexe Ahmadoul Khadim de Touba APS SENEGAL-ADMINISTRATION-FORMATION / Lutte contre les crimes financiers : l’ONRAC et le CFJ mutualisent leurs actions ANP Niamey :La Fifa inspecte les installations du centre technique de la Fenifoot ANP Rabat : Création du Réseau des Journalistes Fact-Checkers des Agences de Presse Africaines (RJF-FAAPA) MAP SAR le Prince Moulay Rachid préside à Meknès un dîner offert par Sa Majesté le Roi en l’honneur des invités et participants à la 16ème édition du SIAM Inforpress Olavo Correia no encontro dos chefes de Estado africanos para identificar principais prioridades de financiamento Inforpress Jogos Olímpicos: Preparação para Paris’2024 está a ser a melhor na história de Cabo Verde – presidente do COC Inforpress Governo autoriza aval à Cabnave para recorrer a empréstimo de 65 mil contos junto à banca

CoST Procurement Engineers validate assurance findings


  22 Décembre      62        Société (45129),

 

Takoradi, Dec. 22, GNA- Engineers with the various District Assemblies have been called upon to enhance monitoring and supervision on contracts to ensure that contractors delivered on projects scope and specifications.
Dr Matthew Somiah, Lead Assurance Professional, serving as a consultant for the Infrastructure Transparency Initiative project (CoST), in the Sekondi Takoradi Metropolis indicated that doing so would help promote value for money as well as quality infrastructure for all.
He said though the Assemblies have the human resources, they lacked the logistics to enable them mobilize to site for effective projects monitoring and execution.
Dr Somiah told the Ghana News Agency during a validation workshop on the second assurance processes commissioned by the CoST on eight procuring entities within the Western Region.
The procuring entities include, Nzema East, Tarkwa, STMA, Wassa East and Shama among others.
The Assurance processes looked at various development projects and their level of disclosure and effective engagement with projects beneficiaries.
Dr. Somiah said some projects have also exceeded quantum and lacked quality.
He therefore suggested that the Assemblies adopted a system where a clerk of works would be stationed at the various projects site to ensure that contractors worked within projects specifications, scope and timelines to meet both sponsors and stakeholders expectations.
Mr Abu Mahama, the Shama Planning Officer, termed the exercise as an eye opener, adding, « there are things we have overlooked over the years which is critical to projects beneficiaries ».
Mr Isaac Aidoo, the CoST Sekondi Takoradi Manager, said the validation was to ensure that the Assurance professionals’ findings tallied with realities on the ground.
GNA